Updates

  • January 2012
    Now that the Genesis Centre of Community Wellness is officially opened, it is time to transition this website and shut-down effectively February 29, 2012. For ...

  • September 2011
    Work begins on floor finishes. Floor and wall tiling begins. Grass is laid on exterior fields. Concrete pad in the soccer field house is poured. Daycare space nears completion.

  • August 2011
    Exterior concrete poured. Most of the landscaping completed. Wood paneling goes up on interior walls.

  • July 2011
    Work on building exterior nears completion.

  • June 2011
    Windows begin to be placed.

  • March 2011
    Work begins on the roof.

  • February 2011
    Work is underway to enclose the building, making it watertight.

  • November 2010
    Structural steel work begins.

  • September 2010
    Walls begin to become visible and take shape.

  • August 2010
    Piles and concrete columns start to go up.